NYAB strengthens its position in Swedish grid expansion

By Christoffer JennelAnalyst
NYAB

Summary

  • NYAB has signed a collaboration contract with Svenska kraftnät for a new 400 kV power line in Norrbotten, with the project divided into two phases, starting with planning and design activities.
  • The total project value is estimated at 136 MEUR, representing a significant portion of NYAB's projected revenue, supporting growth estimates for 2026–2028.
  • Phase 2, the larger construction stage, is expected to begin in Q1 2026, and its potential signing could positively impact NYAB's financial forecasts.
  • The agreement highlights NYAB's strategic positioning in energy infrastructure investments driven by the green transition in Northern Sweden.

This content is generated by AI. You can give feedback on it in the Inderes forum.

NYAB announced that it has signed a collaboration contract with Svenska kraftnät, for the construction of a new 400 kV power line of roughly 100 kilometers between Letsi and Svartbyn in Norrbotten. The project will be executed in two phases. The now-signed agreement covers Phase 1, which includes planning and design activities. Phase 2, the substantially larger construction and commissioning stage, is scheduled to begin in Q1 2026 and conclude in Q4 2028. While Phase 2 will be agreed upon separately, and yet to be signed, we believe the collaborative project model and NYAB’s proven track record with Svenska kraftnät, including the Aurora Line, make it likely that NYAB will receive the full construction order. The total value of the two-phase project is estimated at 136 MEUR (1.5 BNSEK)

The order strongly supports our growth estimates for the coming years

While we expect the value of Phase 1 to be limited (the company did not disclose a figure), Phase 2 would be significant in size. The total project value represents around 22% of our 2026 revenue estimate (614 MEUR), and around 7% on an annualized basis over the three-year construction period. Thus, if fully realized, the order would provide great visibility and a solid foundation for our 2026–2028 growth forecasts (currently 12–7% organic growth), which could prove conservative, particularly for 2027–2028. Overall, we feel this agreement is yet another confirmation of the company's ability to capitalize on the massive investments in energy infrastructure driven by the green transition in Northern Sweden.

The release does not cause immediate changes to our estimates or view of the company, as the value-driving Phase 2 contract remains to be formally awarded. However, we expect a potential signing to occur within the coming quarters, possibly also the Phase 2 of Uppsala Tramway (~447 MEUR, with the partner Azvi), which, if secured, would put upward pressure on our estimates. Our latest company report on NYAB is available here.

Login required

This content is only available for logged in users

Create account

NYAB provides services within engineering, construction and maintenance with a focus on sustainable infrastructure and renewable energy. The offering includes roads, railways, bridges, airports, wind and solar power and power grids. NYAB also provides various types of facilities for industrial customers. NYAB operates in Sweden and Finland in both the private and public sectors.

Read more on company page

Key Estimate Figures06.11.

202425e26e
Revenue345.9549.1613.7
growth-%23.4 %58.7 %11.8 %
EBIT (adj.)26.433.140.1
EBIT-% (adj.)7.6 %6.0 %6.5 %
EPS (adj.)0.030.030.04
Dividend0.010.010.01
Dividend %2.3 %2.3 %2.6 %
P/E (adj.)15.315.512.4
EV/EBITDA9.19.77.5

Forum discussions

NYAB Strengthens Its Position in Swedish Grid Expansion NYAB announced that they have signed a cooperation agreement with Svenska kraftnät for...
11/13/2025, 7:22 AM
by Jesper Hagman
9
Hello everyone! We have recorded an analyst interview about NYAB, however, in Swedish. But for everyone who wants to, you can watch it here:...
11/7/2025, 1:31 PM
by Jesper Hagman
3
Here is a new company report on NYAB from Jenneli. NYAB’s Q3 revenue was in line with our forecast, but operating profit fell short of expectations...
11/6/2025, 9:39 AM
by Sijoittaja-alokas
2
We have also published a CEO interview we recorded today with NYAB’s CEO Johan Larsson. What do you think about NYAB? Inderes NYAB Q3´25: Sweden...
11/5/2025, 12:46 PM
by Jesper Hagman
5
Here are Christoffer’s comments in Finnish. (Christoffer’s comments in English below) NYAB’s Q3 revenue met our forecasts, but reported operating...
11/5/2025, 11:34 AM
by Sijoittaja-alokas
2
Analyst Christoffer’s initial thoughts on NYAB’s Q3 report. “NYAB’s Q3 revenue was in line with our estimate, but reported EBIT was lower. Organic...
11/5/2025, 9:11 AM
by Jesper Hagman
4
NYAB published its Q3 report this morning. “High growth and increased operating profit” If you want to read the full report, it’s available ...
11/5/2025, 7:54 AM
by Jesper Hagman
3
Find us on social media
  • Inderes Forum
  • Youtube
  • Facebook
  • Instagram
  • X (Twitter)
  • Tiktok
  • Linkedin
Get in touch
  • info@inderes.fi
  • +358 10 219 4690
  • Porkkalankatu 5
    00180 Helsinki
Inderes
  • About us
  • Our team
  • Careers
  • Inderes as an investment
  • Services for listed companies
Our platform
  • FAQ
  • Terms of service
  • Privacy policy
  • Disclaimer
Inderes’ Disclaimer can be found here. Detailed information about each share actively monitored by Inderes is available on the company-specific pages on Inderes’ website. © Inderes Oyj. All rights reserved.