Goodtech has signed a contract with Noranett for the modernization of Skistua
transformer station in Narvik. The project will strengthen critical power
infrastructure in a region preparing for increased activity and international
attention ahead of the FIS Alpine World Ski Championships in 2029.
Goodtech's contract scope has an estimated value of approximately NOK 17
million and includes engineering, project management, procurement,
installation, testing, commissioning and documentation of a complete indoor
medium-voltage switchgear and control system. Handover is scheduled for Q4
2027.
The contract will be added to Goodtech's order backlog and supports the
company's targeted growth within critical infrastructure, electrification and
digital control systems. The delivery will contribute to a more robust and
future-ready power system in the Narvik region.
"Reliable power infrastructure will be an important part of enabling growth,
activity and safe operations in the Narvik region. We are proud to be selected
for this project, and the contract plays directly to our strengths within
power systems, automation and digital control, and supports our ambition to
grow in an attractive market segments," says Margrethe Hauge, CEO of Goodtech
ASA.
"Upgrading Skistua is an important investment in the power supply for Narvik.
We need a partner with solid expertise in medium-voltage systems and digital
control, and a proven ability to deliver complex projects safely and on
schedule. Goodtech met those requirements, and we look forward to a close and
constructive collaboration throughout the project," says Tony Molund, managing
director at Noranett.